Preview KPIs are a precomputed sample. Three duration columns are scenarios, not a finish-date probability. Time is working days; weekends are skipped.
No live result yet. Load the sample and run a comparison.
Edit activities, predecessors (pipe-separated) and resource columns. A cycle is rejected before the solver. start_lock ≥ 0 freezes an already-started activity.
activities (durations, predecessors, resource demand)
renewable resources
renewable resources
resource_id | name | name_fa | capacity | reduced_capacity |
|---|---|---|---|---|
R-crane | Install crew | تیم نصب | 6 | 4 |
milestones (due_day is a working-day index)
milestones (due_day is a working-day index)
milestone_id | name | name_fa | activity_id | due_day |
|---|---|---|---|---|
M-01 | Mechanical complete | آماده برقدار کردن | A-08 | 16 |
working-day calendar
working-day calendar
day_index | date | weekday | weekday_fa | is_weekend |
|---|---|---|---|---|
10 | 2026-10-05 | Wednesday | چهارشنبه | 0 |
units dictionary
units dictionary
field | unit | note |
|---|---|---|
crew / elec / crane / super | working-day index | Renewable demand while the activity is in progress |